Have process planning activities been specified and scheduled (e.g. general deadline schedule, project schedule)?
Is the schedule in agreement with the current higher-level project schedule (e.g. QA/review, release dates, pre-series, start of production (SOP), component release/preparation)?
Are costs calculated (investment appraisal with material/ work area/MAE… costs)?
"Are time blocks scheduled for
- capacity testing, (MAE) target specifications
- MAE procurement and acceptance (incl. tools/measuring and test equipment/SW)
- creation of production/process documentation
- packaging preparation for products, parts, materi"
"- Initial operation
- Personnel training?"
Have the resources for implementation of serial production been arranged?